HyperTransfer · Veneto, Italy

Sebuah proyek yang dipromosikan, sebuah konsorsium yang dirakit, satu fase yang diserahkan.

Fase 1 selesai Fase 2 menunggu aktivasi

Hyperworks mempromosikan Hyper Transfer di Italia dan pembentukan koalisi industri yang menjadi Hyperbuilders. Konsorsium Webuild–Leonardo kemudian memenangkan tender CAV dan menyelesaikan fase pertama dari tiga fase program.

Explore the results
HyperTransfer station with a capsule at a covered terminal
Station visualisation supplied by Hyperworks
Aerial visualisation of the HyperTransfer station in Veneto
Veneto station visualisation supplied by Hyperworks
Hyper Transfer capsule concept on an elevated guideway
Hyper Transfer capsule concept · visual supplied by Hyperworks
2022

Peluncuran Italia

MIT · Wilayah Veneto · Protokol CAV

08.05.23

Tender diberikan

Hyperbuilders · Webuild + Leonardo

12.11.24

Fase 1 selesai

Penilaian kelayakan positif

03.06.25

Hasil publik

Presentasi CAV di Munich

Sekarang

Menunggu Fase 2

Desain tetap bergantung pada aktivasi dan pendanaan

Hyperworks’ role

01 / 03

Dari ide menjadi kapasitas industri.

Hyperworks, yang sebelumnya Hyperloop Italia, mempromosikan proyek di Italia, membangun hubungan institusional dan industri, dan membantu membentuk kelompok yang menjadi Hyperbuilders. Tender publik mengubah momentum itu menjadi program yang dikelola secara formal oleh CAV.

Transparansi sumber: peran asal Hyperworks adalah akun perusahaan; penghargaan, manajemen, dan hasil Fase 1 didokumentasikan oleh CAV, Wilayah Veneto, dan sumber proyek.

Hyperbuilders + public governance

Organisasi yang membuat program ini kredibel.

01

Promotion and coordination

Hyperworks

Promoted the project in Italy and the industrial coalition later formalised as Hyperbuilders. This originating role is reported as Hyperworks’ company history.

02

Contracting authority and PPMO

CAV

Concessioni Autostradali Venete led the innovation partnership, operational management and publication of the results.

03

Public management

MIT + Regione del Veneto

They sit with CAV on the Technical Committee and define the institutional and funding framework for later phases.

04

Hyperbuilders consortium

Webuild + Leonardo

A global infrastructure leader and a major aerospace, defence and complex-systems group: together they won the tender and delivered Phase 1.

05

Integration and certification

Italferr + Italcertifer

The FS Group companies supported system integration, railway engineering and the route toward approval and certification.

06

Technical-scientific expertise

Università di Padova

Supported the PPMO and produced independent expert assessments of technology maturity and transferability.

07

Appointed designers

Hyperworks + RINA + HyperloopTT

Design, engineering, quality assurance and hyperloop technology capabilities integrated into the feasibility assessment.

08

Technology and research

Rete specialistica

Thyssenkrupp, PROSE, WayAssauto and the Milan, Turin and Bari polytechnic universities contributed specialist expertise.

Studi kelayakan · ringkasan

Hasil studi kelayakan.

Phase 1 was a full feasibility assessment, run by the Hyperbuilders consortium under contracting authority CAV and closed with a positive outcome. This is a summary of how it was organised, against which criteria, and what it established.

01

Objective of the study

To verify the feasibility of designing, building and testing an ultra-fast, magnetically levitated, low-energy transport system, laying the basis for an innovative, sustainable and commercially competitive transport mode.

02

Instrument: the innovation partnership

The innovation partnership brought together the public side (MIT, Veneto Region, CAV) and industrial capability (Webuild–Leonardo) in a collaborative model, with a PPMO run by CAV and the University of Padua, a Technical Committee, and Italferr and Italcertifer as system integrators.

03

How the work was organised

Eight technical groups covering vehicles, infrastructure, system integration, certification and approval, and stations; four management groups covering economics, multidisciplinary coordination and intellectual property; weekly meetings and workshops with CAV’s PPMO. The work spanned eight countries and over 1,000 hours of conference calls.

04

Guiding criteria

Wherever possible, select technologies that are already commercially available, tested or designed and obtainable without proprietary patents or licences. This lowers technology risk and ties the system to verifiable components.

05

Technology maturity (TRL and MRL)

Every subsystem was assessed on NASA-derived TRL (1–9) and MRL (1–10) scales. The largest challenges remain ultra-high speed in vacuum, thermal-exchange management, the capsule’s enclosed environment and continuous data-transmission requirements.

06

Medium-term industrial spillovers

Some of the technologies developed already improve existing high-speed systems in the medium term: inverters, braking and cooling systems, communication and signalling, aerodynamics and on-board energy sources.

Phase 1

Feasibility assessment

Completed with a positive outcome on 12.11.24

Phase 2

Design

Subject to activation and funding

Phase 3

Prototyping and field testing

Construction of the Test Track (pilot route)

CAV public data · Phase 1

Apa yang dihasilkan studi.

Ringkasan editorial Hyperworks dari hasil yang dipublikasikan oleh CAV. Angka-angka ini menggambarkan studi dan sistem yang diusulkan, bukan infrastruktur yang sudah dibangun.

50,000engineering hours
60FTEs involved
5,000+pages produced
20nationalities
01

Arsitektur yang diusulkan

Jalur pengujian elevated sekitar 10 km, tabung bidireksional tunggal, operasi otomatis, dan tekanan referensi awal 50 Pa yang akan dikonfirmasi selama desain.

02

Kendaraan dan kinerja

Target jalur pengujian 630 km/jam; kapsul untuk 38 penumpang atau 12 ton kargo. 1.000 km/jam hanya dinyatakan sebagai tujuan rute komersial masa depan.

03

Keselamatan dan persetujuan

Rencana manajemen keselamatan, register bahaya awal, bukaan evakuasi, isolasi seksi, dan matriks persyaratan dan standar awal.

04

Pertanyaan yang masih harus divalidasi

Kecepatan ultra-tinggi dalam vakum, pertukaran termal, lingkungan tertutup kapsul, transmisi data berkelanjutan, dan urutan pemompaan di jalur panjang.

Energi: indikasi, bukan janji.

Perbandingan energi CAV adalah model awal untuk rute hipotetis 250 km, dengan tingkat kepercayaan 70% yang dinyatakan, untuk divalidasi selama fase desain.

Transport assessment

Di mana model menjadi kompetitif.

150 km

Kereta tetap umumnya lebih kompetitif; Hyper Transfer membaik untuk penumpang solo selama jam sibuk yang padat.

300 km

Kereta cepat memimpin. Hyper Transfer menjadi sebanding di atas 4 juta penumpang tahunan dan lebih rendah daripada udara.

500 km

Hyper Transfer muncul sebagai opsi paling kompetitif di atas 4–5 juta penumpang tahunan per pasangan asal-tujuan.

700 km

Udara memimpin secara umum; di atas 4–5 juta penumpang tahunan, Hyper Transfer menjadi lebih menguntungkan bagi pengguna.

Simulasi membandingkan mobil, kereta api berkecepatan tinggi, udara, dan sistem Hyper Transfer komersial hipotetis dalam konteks Italia. Ini bukan perkiraan permintaan atau profitabilitas.

Project film · Italian

Tiga menit di dalam Hyper Transfer.

Film ini menyajikan program, pekerjaan multidisiplin, dan visi jalur pengujian melalui rekaman langsung dan visualisasi konsep.

Urutan fotorilistis adalah visualisasi proyek, bukan rekaman infrastruktur Hyper Transfer yang ada.

Running time 03:20 · Italian audio

Open results · CAV

Hasilnya, dalam bahasa Italia dan Inggris.

Hyperworks membuat salinan publikasi yang disediakan tersedia. Hak kekayaan intelektual, data, dan hasil tetap atribut ke CAV dan tata kelola proyek.

Verified status · 28 Jul 2026

03 / 03

Fase 2 belum dimulai.

Fase 1 ditutup dengan positif. Langkah berikutnya adalah desain prototipe dan jalur sertifikasi. Menurut dokumen CAV, aktivasi Fase 2 dan 3 tetap bergantung pada keberhasilan fase sebelumnya dan pendanaan aktual, dengan sumber nasional dan Eropa yang masih harus diidentifikasi.

Hyperworks siap mendukung kelangsungan program, tetapi jalur pengujian belum didanai, dikontrak, atau dibangun.